Study on the insulation level of the gap between UAV and typical high voltage equipment in 110 kV substation
substation,UAV,electric field,simulation,Insulation
终稿
Huipeng Li / School of Electrical Engineering and Automation, Wuhan University
Daochun Huang / School of Electrical Engineering and Automation, Wuhan University
Tianli Yang / Changsha power supply company of State Grid Hunan Electric Power Co., Ltd.
You Li / State grid Hunan extra high voltage substation company
Jianjun Zhang / State grid Hunan extra high voltage substation company
Yunya Zhou / State grid Hunan extra high voltage substation company
Jiangjun Ruan / School of Electrical Engineering and Automation, Wuhan University
Mingjing Shuang / School of Electrical Engineering and Automation, Wuhan University
Study on the insulation level of the gap between UAV and typical high voltage equipment in 110 kV substation

Huipeng Li1*, Daochun Huang1, Tianli Yang2,You Li3, Jianjun Zhang3, Yunya Zhou3, Jiangjun Ruan1, Mingjing Shuang1

1School of Electrical Engineering and Automation, Wuhan University, Wuhan 430072, China

 2Changsha power supply company of State Grid Hunan Electric Power Co., Ltd., Changsha 410015, China

3State grid Hunan extra high voltage substation company, Changsha 410004, China

*lhp2021@whu.edu.cn


Purpose/Aim

UAV has great advantages in the substation inspection by virtue of its flexibility and efficiency. It is of great significance to study the insulation level of the gap between the UAV and the high voltage equipment during the inspection process for the safe operation of the UAV.

Experimental/Modeling methods

The three-dimensional modeling software is used to establish the models of UAV and typical equipment in 110 kV substation, and obtain the electric field and potential distribution between UAV and typical high voltage equipment through electric field simulation. Based on the simulation results, the change of gap insulation level in the process of UAV approaching high-voltage equipment is studied.

Results/discussion

Based on the average breakdown voltage gradient of the typical gap, the breakdown distance of the UAV approaching the typical equipment of a 110 kV substation from different directions is about 10 cm. The research results are close to the results of the UAV approaching the transmission line of the same voltage level.

Conclusions

The change of insulation level when the UAV is close to the typical equipment of 110 kV substation is studied, and obtain the critical discharge distance when the UAV is close to the high voltage equipment. The research results can provide a reference for the safe distance control and path planning of the UAV in the substation.

Appendix


 
重要日期
  • 会议日期

    09月25日

    2022

    09月29日

    2022

  • 08月15日 2022

    提前注册日期

  • 09月10日 2022

    报告提交截止日期

  • 11月10日 2022

    注册截止日期

  • 11月30日 2022

    初稿截稿日期

  • 11月30日 2022

    终稿截稿日期

主办单位
IEEE DEIS
承办单位
Chongqing University
移动端
在手机上打开
小程序
打开微信小程序
客服
扫码或点此咨询